Building Plan Approval in Bengaluru 2026: BBMP to GBA Explained

Building Plan Approval in Bengaluru 2026: BBMP to GBA Explained

By Vishwanath, Founder and Chief Architect, Nisarga Construction 


If you're planning to build a house in Bengaluru, the first real step isn't the foundation. It's the sanctioned building plan. And in the last year, who approves it has changed.

What changed: BBMP is now the GBA

The Greater Bengaluru Governance Act, 2024 established the Greater Bengaluru Authority (GBA), a decentralised, three-tier body overseeing five new municipal corporations across North, South, East, Central and West Bengaluru.

For homeowners, the key point is this: building plan approvals, Occupancy Certificates (OCs) and other construction-related approvals will now be processed by the respective city corporation responsible for your property's jurisdiction. The approval process remains largely the same, although the administrative authority may change.

What to do first: find out which of the five corporations your plot falls under. Ward boundaries were redrawn, so your old BBMP zone may not match your new corporation.

Before you apply: check your plot

  • e-Khata. This is now required before you can apply. If you don't have an E-Khata, your application won't even leave the starting block.
  • Khata type. A-Khata is what you need. B-Khata properties usually need regularising first.
  • Land use. If the plot was originally agricultural land, it needs a conversion order before you can apply.
  • Zoning. Confirm whether your plot is zoned residential, mixed-use or commercial in the master plan.

Can you apply yourself?

No. You cannot apply yourself. You must hire a BBMP-registered architect or engineer to design and submit your plans.

Documents you'll need

Typically:

  • Sale deed / title deed
  • e-Khata certificate and extract
  • Encumbrance Certificate (EC)
  • Latest property tax receipt
  • Architectural drawings (site plan, floor plans, elevations, sections), digitally signed by your architect
  • Structural drawings signed by a licensed engineer

The step-by-step process

  1. Confirm your corporation and zoning.
  2. Hire a registered architect. They design the house within the setback, FAR, height and parking rules.
  3. Online submission. Applications are filed digitally. The process is now digitized through the Nambike Nakshe and OBPAS portals.
  4. Automatic rule check. The system checks your drawings against the building bye-laws.
  5. Site inspection. An engineer visits to check boundaries, road width and site conditions.
  6. Approval. You receive the sanctioned plan and building licence.

Understanding FAR (in plain terms)

FAR is the ratio of the total built-up area of all floors to the size of the plot. For example, if you have a 1,000 sq ft plot and an FAR of 1.5, you can build a total of 1,500 sq ft across all floors. This is why two plots of the same size can allow very different houses.

How long does it take?

Timelines vary by plot, documents and corporation. Most guides put residential approvals at roughly 30–45 working days when documents are complete. There's also a safeguard: under the Sakala guarantee, if BBMP does not raise any objection within 30 working days, the plan receives deemed approval.

After approval

  • Keep the approved plan displayed at the site for the whole build.
  • Build exactly to the sanctioned plan. Deviations cause trouble at Occupancy Certificate stage.
  • Get your Occupancy Certificate (OC) once construction is complete. You'll need it for permanent water and power connections.

Common reasons plans get delayed or rejected

  • Missing or mismatched e-Khata details
  • Setback violations
  • Exceeding the permitted FAR or height
  • Unconverted agricultural land
  • Plot boundaries that don't match the documents

FAQs

Who approves building plans in Bengaluru now?
Your local city corporation under the Greater Bengaluru Authority, based on where your plot is.

Is BBMP plan approval still valid?
Yes. Approvals issued by BBMP before September 2025 remain valid. New applications go through the relevant corporation.

Do I need an e-Khata for plan approval?
Yes. It's now a prerequisite.

How long does building plan approval take in Bangalore?
Usually around 30–45 working days for a residential plot with complete documents.

Can a construction company handle approvals for me?
Yes. A turnkey contractor coordinates the architect, drawings and submission as part of the project.


Building in Bengaluru?

Nisarga handles plan approval coordination as part of every turnkey build — drawings, submission and follow-up — so you can focus on your home, not paperwork.